Thank you, Sustaining Corporate Members, for your investment in the industry! ASA Sustaining Corporate Members show true dedication to ASA’s vision to see “structures built or repaired with the shotcrete process accepted as equal or superior to cast concrete.” These industry leaders are recognized for their exemplary level of support for the Association in a variety of ways. CLICK HERE for reasons why you should consider becoming an ASA Sustaining Corporate Member!
Sustaining Member
Sustaining Member
Sustaining Member
Sustaining Member
Sustaining Member
Sustaining Member
Sustaining Member
Sustaining Member
Sustaining Member
Sustaining Member
Sustaining Member

Sustaining Member
Sustaining Member
When applying 6 in. (152 mm) of shotcrete on an exterior concrete surface, how long should that cure before coating with an acrylic elastomeric roof coating? What is the moisture content of that thickness after 7 days, or after 14 days?
Shotcrete is just a placement method for concrete. Thus, the in-place material will have the same characteristics as concrete. You should consult the coating supplier to establish how long they want the concrete surface cured. They may also specify a certain limit for surface moisture conditions. There are several methods for evaluating the moisture content of the in-place concrete. Here are the ASTM standards that deal with surface moisture:
- ASTM F710, Preparing Concrete Floors to Receive Resilient Flooring; Section 5.2, pH Testing;
- ASTM F1869, Measuring Moisture Vapor Emission Rate of Concrete Subfloor Using Anhydrous Calcium Chloride;
- ASTM F2170, Determining Relative Humidity in Concrete Floor Slabs Using in situ Probes;
- ASTM F2659, Preliminary Evaluation of Comparative Moisture Condition of Concrete, Gypsum Cement and Other Floor Slabs and Screeds Using a Non-Destructive Electronic Moisture Meter; and
- ASTM F3191, Field Determination of Substrate Water Absorption (Porosity) for Substrates to Receive Resilient Flooring.
In addition, The International Concrete Repair Institute (ICRI) has a certification program, “ICRI Concrete Slab Moisture Testing Technician—Grade 1.”
How thick would you recommend a shotcrete application be to make bedrock reservoir waterproof?
There are many variables that would need to be considered to answer your question. Water flow, depth of the application, and overall geometry can influence the required thickness. This is a question that should be addressed by an experienced engineer who can ascertain the required structural properties to resist the hydraulic loads for the depth and geometry of your application. You may find consultants who are ASA Corporate Members in our Buyers Guide.
Is there any article or reference referring to the procedure of maturity of the concrete applied to the shotcrete? Basically, explaining how to generate the validation curves?
Shotcrete is a placement method for concrete. Thus, generating the maturity curves are based on the concrete mixtures. There are several online resources about the maturity method. The Minnesota DOT provides a PDF resource that discusses production of the curves.
How much shotcrete coverage over No. 4 reinforcing bar is required?
Shotcrete is simply a placement method for concrete. The specified concrete cover over reinforcing bar is usually included in contract documents for construction and values vary depending on exposure conditions. ACI 318 provides cover requirements for structural concrete in buildings, and ACI 350 provides cover requirements for concrete liquid-containing structures. Local building codes and fire codes may also require specific cover in concrete construction. If your project doesn’t specify the cover requirements, we recommend you consult with a professional engineer experienced in the type of project you are working on to learn what the code requirements may be.
What is the best way to check the sand-to-cement ratio in gunite batch trucks? Is it normal (common) to get up to 10% air straight from the mixing auger? I had a gunite truck fill a 5 gal. (19 L) bucket with mixed material (sand and cement) then put it in my lab mixer and wetted it up to a 3 in. (75 mm) slump and ran a test for air, unit weight, and cast a set of cylinders. I am trying to figure out the sand-to-cement ratio, but I don’t have a cement diverter to run a real-time sand-to-cement ratio test, so I am testing dispensed material to see if it makes 70% strength in 7 days, which indicates a good mixture. Are there any other ways of checking sand-to-cement proportions? I tested the mixed material in a lab about 5 minutes after it was dispensed.
By “gunite batch truck” we assume you are referring to a volumetric mixer supplying material for a dry-mix shotcrete operation. Gunite is the original tradename for what we now call dry-mix shotcrete. Here’s the description from an ACI Materials Journal (January-February 1991 issue) article about the calibration of volumetric mixers:
“To insure production of quality concrete, each volumetric-measuring unit must be calibrated for each respective concrete ingredient, following the manufacturer’s recommendations and ASTM C 685. These ingredients must be the same as those to be used in actual concrete production. The measuring devices for aggregates, cement, and dry admixtures are calibrated by weighing the discharged ingredient. Devices for water, latex modifier (if required), and liquid admixtures such as air-entraining and water-reducing admixtures generally are calibrated by weighing or measuring the volume of the discharged ingredient. The objective of calibration is to coordinate the discharge of all concrete ingredients to produce the proper mixture.”
ASTM C685/C685M states, “The proportioning and indicating devices shall be individually checked by following the equipment manufacturer’s recommendations as related to each individual concrete batching and mixing unit. Adequate standard volume measures, scales, and weights shall be made available for the checking accuracy of the proportioning mechanism.” Thus, you need to check with your equipment supplier for their recommended procedures to verify batching. Because concrete mixtures always are based on weight of ingredients there you will need to weigh a given volume to confirm the batching is accurate.
The air content test is a measure of total air so includes both entrapped and entrained air. Ten percent is definitely high. The 10% air is likely not representative of the in-place shotcrete. It may have been an issue with the lab mixer introducing more entrapped air for some reason. Estimating the air content from the unit weight test requires a good value for the theoretical unit weight. I’m not sure if you have that with the volumetric batching. You should run the air meter test (ASTM C231/C231M) to measure the air content to get a more accurate assessment.
Regarding the verification of mixture proportions, this is from ASTM C685/C685M:
“7.5 Proportioning Check—Whenever the sources or characteristics of the ingredients are changed, or the characteristics of the mixture are noted to have changed, the purchaser is permitted to require a check of the fine aggregate content and the coarse aggregate content by use of the washout test. Essentially, in the washout test, 1 ft3 [0.03 m3] of concrete is washed through a No. 4 [4.75-mm] sieve and through a No. 100 [150-µm] sieve; that retained on the No. 4 sieve is normally considered coarse aggregate whereas that passing the No. 4 and retained on the No. 100 sieve is considered fine aggregate. Corrections to the quantity of aggregates (per cubic foot or cubic meter of concrete) shall be made if the original sieve analysis of each aggregate is available.”
Because you are only interested in the sand and cement, you can simply weigh the sample of concrete, then wash out all the cement, and then weigh the remaining sand. You would need to bring the sand to roughly the same moisture content as the sand in the truck, so you aren’t including in the weight of excess water in the sand. You should note that with shotcrete impact during placement we will generally lose 50% of the air content, so your final in-place air should be around 5%. That is a reasonable value for good freezing-and-thawing durability.
I would like to better understand the limitations related to the height of install when it comes to the gunite application. Because gunite is a dry concrete mixed with water at the nozzle of the applying apparatus, I have been told by others in the industry that the application is only intended for use of walls less than 4 or 5 ft tall. If that is the case, is it safe to assume that the gunite application strategy should not be used for below-grade vaults exceeding a height of 5 ft? I am looking for design literature specific to gunite.
Dry-mix shotcrete adds mixing water to the dry concrete materials as the concrete materials flow through and out the nozzle. Gunite is the original tradename for dry-mix shotcrete. Though you may not find design information using the old gunite name, you will find numerous current design references to dry-mix shotcrete. This includes ACI 506R-16, “Guide to Shotcrete”; ACI 506.2-13, “Specification for Shotcrete”; ACI 506.6T-17, “Visual Shotcrete Core Quality Evaluation Technote”; ACI 372, “Design and Construction of Circular Wrapped Prestressed Concrete Tanks”; ACI 350-06, “Code Requirements for Environmental Engineering Concrete Structures”; ACI 350.5, “Specifications for Environmental Concrete Structures”; and seven ASTMs that directly cover shotcrete. ACI 318-19, “Building Code Requirements for Structural Concrete,” has also added specific shotcrete provisions. Dry-mix shotcrete has been used for decades to build structural concrete walls over 50 ft high in circular prestressed concrete tanks that withstand a full head of water pressure. This is a substantially greater water pressure than your 5 ft vault wall would experience. There are no limitations in the dry-mix placement process that would preclude use in high walls. Both dry-mix and wet-mix shotcrete using quality materials, proper equipment, and experienced placement crews will produce in-place concrete of equal strength, durability, and low permeability. However, generally wet-mix shotcrete can offer placement rates up to four times higher than dry-mix. Thus, in thicker, longer walls, wet-mix shotcrete may be more cost-effective because it can be placed faster.
One quick question regarding the “grading” of cores based on 506.2: I imagine the 1995 standard-based 1 through 5 grading system is no longer valid? In one case the special inspector has failed a core (score of 5) simply because a piece of it broke off during the coring and removal from the coring cylinder. I’m leery of that type of failed rating. What do you think about that, and core grading in general?
The current version of the ACI “Specification for Shotcrete” is ACI 506.2-13 and purposely eliminated the core grading due to many problems that arose in the field in trying to equitably apply the procedure. ACI 506 has a new document ACI 506.6T-17, “Visual Shotcrete Core Quality Evaluation Technote,” that is intended to assist specifiers with evaluating shotcrete core quality for an intended use. So yes, the 506.2-95 version of the specification and the grading system it included is no longer supported as an industry standard.
Regarding grading, a shotcrete score of 5 under the deprecated grading system just because the core broke during coring is unreasonable. The coring operation exerts a massive force on the core, as it basically rips it out of the concrete. We have seen many instances where the core snapped where a large reinforcing bar horizontally crossed the core and effectively created a slip plane that reduced the shear resistance of the core section to the torque created by the coring. In those cases, examining the core hole for any evidence of shotcrete problems would be appropriate and then discounting the core itself.
In summary, my position and the ACI 506 Committee’s position is that core grading should not be used for evaluating shotcrete quality. The ACI 506.6T-17 Technote document should be the current reference for making a reasonable evaluation of shotcrete quality for the intended use.
What is the cure time for shotcrete before paint can be sprayed? And what type of paint (latex or oil-based) would work best?
Shotcrete is a placement method for concrete. Thus, cure time is the same as what the coating manufacturer recommends for new concrete surfaces. Because moisture in the concrete surface is part of the concern of bond from manufacturers, a water-based latex may be preferable to oil-based, but you should discuss the appropriate time and materials with your coating supplier.