We are working on a design-build project located in southern California of which the perimeter walls of the underground parking structure are planned to be shotcrete. Do you recommend any particular ACI publication that would be applicable to the shotcrete operation or does ASA have their own publications, similar to ACI, that are more appropriate to shotcreting?

ACI Committee 506 is the technical committee responsible for creating and maintaining the ACI documents related to shotcrete. ACI 506R-16 Guide to Shotcrete is an excellent resource for shotcrete information including materials, equipment, crew composition and placing techniques. It is a non-mandatory document that is very descriptive and readable. ACI 506.2-13 (18) Specification for Shotcrete is another excellent resource that has mandatory requirements for the contractor’s shotcrete placements. Additionally, the ACI 318-19 Building Code Requirements for Structural Concrete directly addresses shotcrete for use in buildings.

A past article in Shotcrete magazine describes the additions to cover shotcrete in ACI 319-19: shotcrete.org/wp-content/ uploads/2020/06/2019Fal_HanskatHollandSuprenant.pdf

Another past article dealing with Shotcrete Testing—Who, Why, When, and How can be found on our website here: shotcrete.org/wp-content/uploads/2020/01/2011Sum_Hanskat.pdf

 

 

Do you have any case studies or applications where Ground Granulated Blast Furnace Slag (GGBFS) cement was successfully used in the concrete mix?

Shotcrete is a placement method for concrete. Concrete mixtures that have been shotcreted have used all different supplemental cementitious materials (SCM) including slag. Silica fume, and fly ash are also widely used. Generally geographic availability and cost of the slag are a deciding factor on if slag is included in a concrete mixture design. Concrete using alternative binders or cements have been used for specialized applications like refractory, or extremely high early strength gain. Here are links to past articles from our Shotcrete magazine that have considered slag in shotcreted concrete mixtures:

The Use of Slag Cement, Alkali-Free Accelerator, and Macro-Synthetic Fibers https://shotcrete.org/wp-content/ uploads/2020/05/2016Spr_Yurdakul-etal.pdf

Sustainable Shotcrete Using Blast-Furnace Slag https://shotcrete.org/wp content/uploads/2020/05/2013Fal_Sustainability.pdf

Our shotcrete contractor started shooting our residential swimming pool on a Friday and stopped 1/3 of way through the process. They plan to restart and complete shooting the pool the following Monday. This site is in Houston and has been averaging 90+ °F (32 °C) average daily temperatures. Aside from soaking the existing pool structure during the hiatus and additional continuous watering through the 10 days after completion to let concrete cure, what steps do I and the contractor need to make to ensure a cold joint will not fail and leak in the future? I will be able to supervise the second shot. What can I do, or make sure the contractor does, to ensure the structural integrity and quality of my investment?

Wet curing of newly placed concrete is certainly important. Your 10-day cure sounds great. Properly placed shotcrete against a properly prepared construction joint will provide concrete that acts monolithically and will not be a “cold joint” as is common in cast concrete. There are three key factors for joint preparation:

  1. The joint must be roughened. This should be done when the crew finished for the day using a stiff broom or raking with a trowel.
  2. On the subsequent shoot the surface should be cleaned (usually using a high pressure, pressure washer).
  3. Before shooting bring the surface to a saturated surface dry (SSD) condition. SSD means the pores of the concrete have been filled with water but there is no running water on the surface.

Following these 3 steps are essential for creating a monolithic, watertight joint. Here’s a link to an article on why shotcrete doesn’t have cold joints: https://shotcrete.org/wp-content/uploads/2020/05/2014Spr_TechnicalTip.pdf

Quality shotcrete placement requires a well-designed concrete mixture, proper equipment, attention to the surface prep, proper placement techniques, and curing. One aspect that can help you ascertain the nozzleman’s expertise is to require they have a current American Concrete Institute Shotcrete Nozzleman Certification. You can verify an individual’s certification status at: https://www.concrete.org/certification/verifyacertification.aspx?d=Ask

 

 

I am looking for information on where, when and why welded wire mesh (WWF) would be recommended in lieu of structural steel reinforcement, or with steel reinforcement, or guidance on how to determine which option or combination is the preferred one.

WWF should only be used when the area of reinforcing provides the required reinforcement area. It may serve as supplemental reinforcement to bars, or entirely replace reinforcing bars as long as the required area of reinforcing steel is provided in the concrete section. Where multiple sheets (more than 2 at say a corner) overlap you may need to cutout one or more of the layers to allow good encasement. Don’t use steel fibers with WWF as they tend to bunch up where the wires cross.

WWF can be used to provide reinforcing in double curved sections where it would be hard to bend and place reinforcing bars. Also, it may be used where you have a thick concrete cover or unreinforced thickness of a repair area that you wanted to get some reinforcing in place to control depth of any surface or shrinkage cracking.

If the mesh is just being provided to help support shotcrete being shot overhead you may not worry about the area of steel, just adding it in addition to the original design reinforcing. Then a lighter mesh might be used since you aren’t really worried about its ability to be reinforcing.

 

 

I work for a Commercial pool builder. We are doing a Jr. Olympic pool (competition pool) 40 ft by 70 ft (12 m by 21 m) with a 20 ft by 10 ft (6 m by 3 m) swim out area with steps. I would rather have the entire pool shot with shotcrete. The office wants the floor poured first then shoot the walls the next day. Can you talk about any advantages or disadvantages to either? Normally we are in a remote location with no power or water. We’ve had issues with shotcrete cracking on the floors and I understand that can happen because of many factors but poured concrete can as well.

Casting the floor first is recommended. Note that rebound and trimmings from vertical wall placement are not fully consolidated concrete and must not be used as part of a structural concrete section. Thus, casting first allows:

  • No collection of rebound and trimmings from wall construction to get trapped below floor reinforcing steel.
  • Provides a stable surface to collect and remove rebound and trimmings.
  • Is generally faster placement and allows full consolidation of concrete throughout the floor thickness by immersion vibrators.
  • If using wet-mix shotcrete the shotcrete pump can serve as a line pump for pumping concrete into the floor thus requiring no extra equipment.
  • Allows proper joint preparation at the floor/wall joint to provide a watertight joint.

 

 

Our pool company just completed the shotcrete today and temperatures are expected to reach near freezing tonight. Should the shotcrete still cure properly? Should we be concerned?

You say near freezing, so we assume it did not reach freezing. Though the newly place concrete will not gain strength quickly it should not be damaged. As temperatures rise during the day the warmer temperatures should allow more strength gain. Concrete has a chemical reaction to build strength, that generates internal heat. If freezing weather was expected, we would recommend use of a protective blanket on the concrete surface to help hold the heat in and promote quicker strength gain. Generally, in concrete we like to see the concrete surface temperature at 50 °F (10 °C) or higher in cold weather to encourage strength gain.

 

 

I am working on a fire re-build project near Napa, CA. The existing building has 12 in. (300 mm) thick shotcrete basement walls. There are many areas where the concrete cover spalled off from the rebar. The rebar appears to be ingood condition with no visible buckling. Is it possible to repair these walls with a 1 1/2 to 2 in. (38 to 50 mm) layer of shotcrete to restore the concrete cover? If so, what sort of surface prep is required? Is a concrete bonding agent required?

Yes, this is definitely a good application for shotcrete. To restore the cover:

  • Chip or hydrodemo back to sound concrete. If a reinforcing bar is more than half exposed, chip at least 1 in. (25 mm) back behind the bar.
  • Make sure the surface is roughened and clean.
  • Bring the concrete surface to saturated surface dry (SSD) condition. This means the surface feels damp but water is not picked up on a hand.
  • Make sure the shotcrete placement is properly executed. Use of an ACI-certified shotcrete nozzleman is recommended.
  • No bonding agent should be used. It will interfere with the natural bonding characteristics of shotcrete placement.
  • If chipping out a section do not feather edge. Provide a ¾ to 1 in. (19 to 25 mm)) depth of cut at the edge to provide adequate thickness for the integrity of the shotcreted material at the edge.

 

This article on the excellent bond between shotcrete provides more detail: https://shotcrete.org/wp-content/uploads/2020/05/2014Spr_TechnicalTip.pdf

 

I’m interested in any information you can provide about recommended expansion/contraction joint spacing for lazy river concrete flumes.

Shotcrete is a placement method for concrete. As the lazy river is a long concrete trough that is intended to be functionally watertight, the best guidance is ACI, 350-06 Code Requirements for Environmental Engineering Concrete Structures. As the predominate stresses in the horizontal direction result from shrinkage and temperature, Section 7.12.2.1 provides guidance on joint spacing based on the provided reinforcement ratio in the concrete section. The closer the movement joints, the less reinforcement required. Chapter 5 of ACI 350.4R-04, Design Considerations for Environmental Engineering Concrete Structures, has guidance on design of joints for water containing structures to help maintain water tightness.

We are working on a large infrastructure project in New York state. We have access and approval issues for a new concrete mixture design. Our understanding is we can specify a Pre-Bagged or Pre-Packaged Shotcrete mix for a wet-mix application. Is this the correct terminology? Are there companies that produce this type of product?

We see both Pre-Bagged and Pre-Packaged terminology used. ASTM C1480 / C1480M – 07(2012) uses the rather unwieldy Standard Specification for Packaged, Pre-Blended, Dry, Combined Materials for Use in Wet or Dry Shotcrete Application.”  Most suppliers of packaged dry concrete materials for shotcrete have formulations designed for wet-mix applications. You can find our corporate members who supply pack-aged materials on our website in the Buyers Guide (shotcrete.org/BuyersGuide), select the Category, Shotcrete Materials-Mixture Sales” and the Subcategory, Wet Mix. 

We are working on a repair/renovation project in Boston. A long-concealed wall next to an adjacent property is now visible as the adjacent property is being renovated. We have been told that our wall must have a 2-hour fire rating. Our wall is composed of CMU masonry and exposed structural steel members. Applying shotcrete to the CMU and steel is a good solution for several reasons. Would you provide shotcrete specifications that will have a 2-hour fire rating on CMU and structural steel?

Shotcrete is a placement method for concrete. Thus, the fire resistance for shotcrete placement is the same as concrete. The primary reference for fire resistance of concrete is ACI 216.1-14(19) Code Requirements for Determining Fire Resistance of Concrete and Masonry Construction Assemblies.