Can you provide any information on insulating gunite in spa installations?

There are two ways to insulate the outside of concrete spas. The first way is to shotcrete the spa and then glue Styrofoam to the outside of the concrete shell or to spray the insulated foam to the outside surface. The second way is to use the ICF (insulated concrete form). You would only have to use one side of this form system. This system would act as the outside form so that the shotcrete could bond to the foam. This type of system has foam insulation thicknesses from 1 to 4 inches thick. Yes, it can be fitted to form circles. Each ICF system is different, so some research would be needed to see which system would work the best. Since most spas are formed up before they are shot, the ICF system would serve two purposes: forming and insulation in one step.

When used on walls, can shotcrete be of equivalent strength as poured concrete?

Basically, shotcrete is a method of placing concrete that does not require forms. As a matter of fact, shotcrete requires the concrete mix to be proper every time. With formed concrete walls, the ready mixed concrete going in can be substandard and still appear to be okay. Shotcrete also provides a more dense concrete less susceptible to water penetration. The most glaring difference will be the quality of the materials used. Most poured walls are designed for a compressive strength of 2500 to 3000 psi. Typically they are placed with a water/cementitious material ratio of 0.60 and higher. Curing is almost unknown in the poured wall sector. Protection only occurs in the coldest weather. By the very nature of the process, shotcrete will have a much lower w/cm ratio. This will produce a wall with higher compressive strength and have the attributes of lower w/cm ratio concrete, i.e. reduced permeability, less shrinkage, increased durability. With proper curing and protection, the shotcrete mixture will produce significantly better long-term performance. The shotcrete process should allow for easier addition of insulation to the walls as well. This is especially important if the basement is to be used for more than just storage.

What is the minimum thickness that shotcrete can be applied? We are currently using shotcrete on a restoration project and have a concern at the corner locations are returning to tight recessed steel framed windows. There is an exterior wood molding approximately 1 inch from the tight corner that needs to be preserved. Do you have any suggestions as to how we can address this? Do we need to provide caulking between the wood molding and the shotcrete?

Thicknesses depend on the structure and surface (surface prep is the key to proper bonding of shotcrete) the shotcrete is being applied to. Depending on the application 1/4 flash coat to 1 inch thickness can be the minimum. As far as shotcrete up to the steel windows, you have to consider that cracking may occur off of each corner. This can be minimized by adding additional reinforcement at those locations. It is common to tool in a joint around the windows so that we could apply a caulk later. The caulking will assure a waterproof seal between the window and the concrete during temperature changes that may create some expansion and contraction. You do not have to depend on the trim work to create the weather and water tight seal the architect requires.

I am looking for design information for shotcreting a steel sheet pile wall to create a composite structure for a lift station wet well. I can design the sheet piling, which would be driven into the ground in a plan circle of 12 feet diameter, followed by excavation. I need to know the practicality of then applying a layer of shotcrete, primarily as a means of sealing the joints of the sheet pile, protecting the sheet pile from the wastewater, and providing additional wall strength. The lift station will be above the water table during construction, but would be periodically below the water table under groundwater conditions.

There are four common types of sheet pile sealing: 1.) all seams were welded to keep the ground water from seeping in, 2.) the sheet pile surface was sandblasted for bonding, 3.) wire mesh was tack welded to the sheet pile and 4.) rebar was tack welded to the sheet piles. This was done prior to the shotcrete layer. In each case the shotcrete is used as a coating to keep the water from touching the piles and in the third and fourth examples, it is used as a structural coating as well.

Is there any reference that differentiates between temporary shotcrete work and permanent shotcrete work, as far as inspection/testing requirements?

Temporary lagging of shotcrete must meet some standard as it is the shoring holding back the earth. If reinforcing is used in the design of the temporary shoring it must be fully encapsulated to provide the design strength of the lagging as specified in the design. A temporary structure may have a low safety factor but the strength of the rebar and shotcrete must meet the design specifications. Many times it is more important to do good shotcrete for the temporary shoring just because it has a lower factor of safety and therefore less allowance for poor construction practices.

My company manufactures a polyester geogrid that is coated with PVC. We sell these grids into underground mines, as well as many aboveground civil engineering products. We have a new grid that may work very well as an auxiliary reinforcement for shotcrete-type products. Can you tell me what the pH is for these products? The type that we would be exposed to is used in underground mines to reinforce the mine roofs.

The most commonly used estimates for pH of concrete are 13 for plastic (fresh) concrete and about 10 for hardened concrete with a little age to it.

I am a general contractor who hired a company to shotcrete a new swimming pool. They began on Friday, a very hot day, and they were placing concrete very slowly (27 yards in 4 hours). Their pump broke down and they were unable to complete the job that day so they returned on Monday. My Question is about the “cold joint” between the work on Friday and the work on Monday. What is your opinion of this situation?

On large swimming pools, it is not unusual to have joints that are left over a weekend or longer. The key is the means by which the joint is dealt with. As with any concrete joint, the surface needs to be clean and free of laitance or other contamination. This can be accomplished by cleaning the joint while it is green on the first day or by cleaning with waterblasting, sandblasting, or wire brushing after the surface has gotten hard. As long as the joint is clean, all gloss has been removed, and the joint is dampened the structure should not be impacted by the joint. Also, 27 cubic yards in 4 hours is not necessarily slow production. Depending upon the circumstances, I would think that 27 cy in 4 hours was quite productive.

Can shotcrete be painted like other concrete? Can an elastomeric paint, 100% acrylic latex house paint or solvent acrylic be used? I have a customer who wants to paint a tank which uses shotcrete. With normal concrete the surface must be 30 days or older, pH is approximately 7-8 and moisture content is low, remove efflorescence or laitance, etc., then it is ready to paint or coat. Do the same restrictions for shotcrete?

Shotcrete is pneumatically applied concrete. All surface prep work for concrete will be the same for shotcrete applications. Before a recommendation can be made, is this tank going to be painted on the outside or the inside? Second if this tank is to be painted on the inside, what will be put in it? The environment in which this tank is located also plays a key part in determining what type of paint or coating application. If this a tank that has been in operation, what was stored in it? Testing of the concrete in this case is important, in order to determine what method of surface prep would be needed to achieve a good coating bond.

I have a project wherein some 25,000 sq ft of existing shotcrete is to undergo varying degrees replacement, repair and restoration. It is on slopes varying from 1:1 to 1:10 or so. It is approximately 40 years old in most cases. It is in a fairly arid climate (Southern New Mexico) with little rainfall and typically low humidity. The subgrade is non-plastic gravelly sandy material. It was reinforced with wire mesh (looks like 6x6x10x10). I’m interested in any techniques and/or materials that might be applicable

I recommend reading the following publications in Shotcrete Magazine: “Shotcrete for Ground Support: Current Practices in Western Canada”, by C.Chan, R Heere, & D. R. Morgan, Part I printed in Winter 2002, and Part II printed in Spring 2002. “Soil and Rock Slope Stabilization Using Steel Fiber Reinforced Shotcrete in North America”, by M.Ballou & M Niermann, Summer 2002.

I am looking for any information regarding the use of construction joints for permanent shotcrete wall facing. I have found information on placing shotcrete over existing construction joints but none regarding the use of construction joints for the shotcrete wall facing itself.

In many experiences, the spacing and design of the joints are the same as you would expect for a cast in place wall. Walls have been constructed with no joint, with contraction and expansion joints, with a joint that is caulked, with joints containing waterstop, and just about anything else you might see in a cast in place wall. In short, it is suggested to look to the direction given for cast in place concrete. The construction joint should be designed similar to the needs of any cast in place wall.