PoolQ We are having a swimming pool built with shotcrete. Our question is, what is the required curing time for shotcrete prior to exposure to heavy rain? We are trying to plan the shotcrete installation when the weather looks most favorable.
Shotcrete needs to be protected from rain until it obtains its final set, usually 4 or 5 hours. Following final set, it should be wet cured for at least 4 days, preferably 7 days if possible. The exposure to rain would prove beneficial as the rain would assure the presence of moisture for continued curing.