Shotcrete is concrete, and therefore if designing structures based on the ACI 318 Code, cover for conventional reinforcing steel should be those suggested in ACI 318 for concrete against ground. If the shotcrete is a “temporary” support, with further placement of “final” support, then these requirements do not apply.