UndergroundQ I am lowering the roof of the draft tube on a hydropower dam. The work is all overhead and has a slope to it. The new roof profile will be lowered from 2 in. (51 mm) (initial edge) to 6.25 ft (approximately 2 m) thick. The plan is to use rock anchors to transfer the load to the existing concrete, and tie in a reinforcing bar grid at the lower section of the new roof profile (4 in. [102 mm] cover). Shotcrete is being planned for the infill material. The traditional ACI 318 design method was used for sizing reinforcing bar. The concern I have in the design is the application of the shotcrete. The plan is to allow the contractor to install a wire mat (or reinforcing bar mat) approximately 2 in. (51 mm) from the existing concrete roof, then apply shotcrete until reaching the reinforcing bar location, up to 6 ft (1.8 m) thick, then apply the finish layers. I have concerns about how thick shotcrete can be applied overhead. I have received feedback from some shotcrete companies that one can apply up to 4 ft (1.2 m) thick overhead layers, yet others say to never apply more than 4 in. (100 mm) layers. I also have concerns of delamination between the shotcrete and the existing concrete during the installation process, and potential shotcrete falling under its own weight in the thicker locations. Do you know of any situation where shotcrete was installed overhead to thicknesses of 6 ft (1.8 m)? How thick can the shotcrete be before additional reinforcement is required to hold it for overhead applications? Is there a recommended maximum thickness for overhead application of shotcrete being placed before additional reinforcement is required? For the area that is 6.25 ft (2 m) thick, should I be using multiple layers of reinforcement (or fiber reinforcement) to prevent fallout?
This is a very challenging potential installation and there could be several potential approaches. For the shotcrete to bond to the existing concrete, the existing surface should be properly prepared, removing any unsound concrete, then roughened and cleaned to allow for a good bonding interface. You mentioned using rock anchors or bolts. These should be installed before any shotcrete.
For each 6 in. (152 mm) layer, a layer of welded wire reinforcement or structural fibers should be used. These, in conjunction with the rock bolts, should ensure the stability of each layer of the shotcrete from falling.
The surface reinforcement should not be installed before most of the area is within 6 to 8 in. (152 to 203 mm) of the final surface.
There is currently similar thicknesses being placed on the East Side Access in New York City to build back the overbreak for the initial tunneling to the “A-line” or profile that was intended for the mining.